Mathematics A, Further H235: Decision Making in Project Management Topical Past Paper Questions
OCR AS Mathematics A, Further (H235) past-paper questions on Decision Making in Project Management, free. This topic is frequently examined across 4 exam sessions. Sign in for the full topic-segregated question bank and AI worksheets.
Sample questions
A project is represented by the activity network below. The activity durations are given in minutes. (a) Give the reason for the dummy activity from event ③ to event ④. [1] (b) Complete a forward pass to determine the minimum project completion time. [2] (c) By completing a backw…
Hiro has been asked to organise a quiz. The table below shows the activities involved, together with the immediate predecessors and the duration of each activity in hours. (a) A sketch of the activity network is provided in the Printed Answer Booklet. Apply a forward pass to dete…
Sarah is having some work done on her garden. The table below shows the activities involved, their durations and their immediate predecessors. These durations and immediate predecessors are known to be correct. (a) (i) Use a suitable model to determine the following. • The minimu…
Sign in required
Full Decision Making in Project Management question set, mark schemes and AI worksheets
Log in for the full topic-segregated question set, mark schemes, and AI worksheets built from every Mathematics A, Further past paper. New accounts start with 25 free credits.
Explore all Mathematics A, Further topics
All Mathematics A, Further topics